mdrejhon
Senior Member
And the Scarborough Cost Overrun Nightmare.TTC is doomed by the spadina fiasco
Metrolinx is in the driver's seat, at the moment, it seems. Accelerated GO expansions, GO RER, ECLRT, UPX, Hurontario....
And the Scarborough Cost Overrun Nightmare.TTC is doomed by the spadina fiasco
See above for the full council resolution
TTC is doomed by the spadina fiasco
Between 2005 and 2009 is when there were ongoing consultations regarding pinpointing the routing and technology, as well as formulation of business plans to support the investment. By 2009, the plan solidified into something roughly 95% similar to what is being built.Wow, between the 1st and 2nd step: 4 years. At least things are actually happening now, which seems like a miracle considering how many elections a transit project has to persist through to actually start construction.
Thank you. Like I said, happy to be proven wrong and I was. The previous council certainly took two different positions in a very short amount of time, but hey, that's what Toronto did on Scarborough so it's happened before.
We'll see what happens next.
If anything is doomed, its the typical style of procurement the City and the TTC went with on the Spadina extension. I'd expect to see Hurontario-Main LRT go through the AFP process provided by Infrastructure Ontario, and that way any risk of cost and schedule overruns are transferred to the private sector. My question if anyone could confirm that it will indeed go through that process is still outstanding.
Given her other issues at the time, it is not surprising that the council decision to carefully defer received a lot less press coverage than the previous week's unanimous vote to, seemingly, kill the thing.
The delays incurred on the TYSSE had nothing to do with how the project was tendered. They were tendered by the traditional design-bid-build approach that's used for most public construction projects, whereby the detailed design is done before the project goes out to tender. The design-bid-build approach can still employ the RFQ/RFP process to screen potential bidders.If anything is doomed, its the typical style of procurement the City and the TTC went with on the Spadina extension. I'd expect to see Hurontario-Main LRT go through the AFP process provided by Infrastructure Ontario, and that way any risk of cost and schedule overruns are transferred to the private sector. My question if anyone could confirm that it will indeed go through that process is still outstanding.
The delays incurred on the TYSSE had nothing to do with how the project was tendered. They were tendered by the traditional design-bid-build approach that's used for most public construction projects, whereby the detailed design is done before the project goes out to tender.
That's a likely bet, given they didn't cancel the order for the 48 cars for the Scarborough line, on the basis they could be used elsewhere.Any idea what type of vehicles they will be using here? The same as those on Eglinton?
A conglomerate bidding on an IO project under the AFP model would simply have more schedule slack, and more contingency to absorb unforseen costs. Sure, there is a lot of incentive to meet the targeted dates, but there is also a lot more leeway on the contractor's part in their ability to do that.I don't buy that the delays had nothing to do with it. The contractor would face penalties for schedule overruns, and therefore has more incentive to pull out all the stops to stay on schedule.