Yes indeed, it went very fast from sales to construction unlike many other projects.
 
lumiere on time

Lumiere's the remaining one 1-bed and three 2-bed suite have been listing on MLS for months. But today I noticed that they have been removed? Have they being sold out recently?
 
Last edited:
May 10th Update

Forms continue to be setup for the ground level (lobby etc.) and some pouring has been done.

Click on the thumbnail to enlarge, then click again on the image for full size.

 
May 23rd Update

This part is always slow.

From Laplante Ave. (w. of Bay St.)

Click on the thumbnail to enlarge, then click again on the image for full size.

 
fundation

why building the foundation part is slower than upper part, although it seems to be obvious?
 
Because the upper part has standard floor plates that allow the use of reusable flyforms for the concrete, while the lower parts require them to build custom forms for everything.
 
June 11-09

From Bay Street. In another two or three weeks this should start to fly up.

Click on the thumbnail to enlarge, then click again on the image for full size.



June 12th, from the south side of Bay St.

 
Last edited:
update by Jasonzed at SSC...

06272009a021.jpg
 