Update:
Rathburn was a warzone Sat with it close between Station Gate to Duke of York for everyone.
No work has taken place on the south pier support since I last shot it, but core drilling for caisson taking place at the intersection in the north-east conner.
Wet Utilities Completed to Date ✔
Watermain - 6.1 Km of pipe installed to date ✔
Storm - 3.3 Km of pipe installed to date ✔
Sanitary - 1.7 Km of pipe installed to date ✔
Total of all wet utilities is 11.5 Kms Dry Utilities Completed to Date ✔
88 Hydro poles installed ✔
5.06 Km of concrete encased underground hydro duct banks installed ✔
6.12 Km of underground hydro cable installed ✔
30.81 Km of aerial conductor installed
Work is to get underway this month for the guideway
Guideway construction in preparation for track installation along Hurontario Street will progress from south to north, beginning between Matheson Boulevard and Britannia Road.
Construction will occur in the mid-block sections (the areas between intersections) with minimal/no impact to pedestrians and traffic flows at intersections for this stage of work.
Work will occur in all of the mid-block zones simultaneously and will take approximately four months to complete in this area.
Once the guideway is constructed, the configuration in the centre of the roadway will be permanent, prohibiting U-turns and left-turns across the tracks at undesignated locations
QEW Push Box
The box will be built on the north side of the North Service off the road. Come Thanksgiving this year, the box will be push onto the road and then south to the QEW overpass. Talks still on going with MTO about closure and no final plan at this time.
Brampton South
● Tree protections
● Staging on both sides of Hurontario Street between Bartley Bull Parkway and Brampton City Limits are expected to begin by the end of March
● Wet Utilities set to begin once traffic staging is complete (watermain, sanitary and storm)
● Installation of guideway, tracks, and OCS poles at the OMSF are ongoing, and connecting guideway infrastructure onto Edwards Boulevard
● Electrical connections and the overhead steel platforms are being installed at the OMSF building Mississauga South
Mississauga South
● Sanitary structure installations will continue along the east side of Hurontario until the end of March
● Hydro Pole, aerial cable works, and duct banks continue along Hurontario
● Alectra relocation are progressing north of Mineola Road towards the QEW
● Site preparation, including clearing and grubbing of vegetation and sidewalk demolition, set to occur near the QEW in advance of the Push Box activities later this year
● Work continues at Mary Fix Creek to expand and revitalize the creek bed
● Work continues at the Lakeshore West Push Box with the construction of a temporary bridge in advance of the underpass installation
Mississauga North
● Storm and watermain installations continue between Eglinton Avenue and Matheson Boulevard as well as between Derry Road and Topflight Drive
● Alectra relocations, road widening, and new curb installations continue between Matheson Road and HWY 401 as well as along Britannia Road, including the installation of transformers and switchgear
● Road widening between Matheson to HWY 407 continues with excavation and the installation of subdrains
● Installation of permanent street light installations continue between Matheson Road and Britannia Road as well as between Derry Road to HWY 407