Where would they put it? I don't think the yard is ready yet.What I meant by "see" was when do we expect to "see" the first ones at the Mount Dennis yard, I am aware they are operating on ION.
When do we expect to see actual track on the surface section of Eglinton and not just cones? If it takes as long as it has to commission the ION line and the Line extension, they had better have substantial construction completion done by end 2020.that is now less than 36 months. As we all agree, specific hard deadlines on completion are not a Metrolinx strength.When do we expect to see the first Eglinton vehicles?
I just re-read a presentation on the Mount Dennis Station and the maintenance facility. Have a look at the last line of the slide attached. It appears to show vehicle delivery in Q4 of this year. Holy cow, folks, we are in 2018.What I meant by "see" was when do we expect to "see" the first ones at the Mount Dennis yard, I am aware they are operating on ION.
Different topic, in terms of actual completed vehicles, here's the score (correct me if I'm wrong)
TTC: 57/204 (Ordered 2009)
ION: 3/17 (Ordered 2013)
I've no idea if they are still fully assembled and operational with all the Metrolinx fuss, or if they have been sacrificed for parts for the almost identical Waterloo vehicles.
With the Waterloo cars almost finished, and the first Eglinton cars not due until late 2018, presumably they are focusing on getting the 10 cars for Edmonton ready for 2018 delivery (with the remaining 16 to follow in 2019 and 2020). And then the remaining 76-car order for Metrolinx with deliveries into 2021.They are still fully assembled and operational. They are being rotated through the testing and tweaking they are doing with the ION vehicles in Kingston.
With the Waterloo cars almost finished, and the first Eglinton cars not due until late 2018, presumably they are focusing on getting the 10 cars for Edmonton ready for 2018 delivery (with the remaining 16 to follow in 2019 and 2020). And then the remaining 76-car order for Metrolinx with deliveries into 2021.
All sounds relatively doable
I just re-read a presentation on the Mount Dennis Station and the maintenance facility. Have a look at the last line of the slide attached. It appears to show vehicle delivery in Q4 of this year. Holy cow, folks, we are in 2018.
Out of curiosity, is it possible to add a section to a Flexity after the fact? Ottawa's stations were all designed with a provision to extend the trains from a 2-car, 98 m train (4 modules per car) to a 2-car 116m train (5 modules per car). The plan is to insert another module when capacity demands it. On the crosstown, the plan is to just add a whole other vehicle, but you end up with a lot of wasted space with 4 cabs and 3 couplers in the middle.
They're expecting 14 Bombardier Freedom vehicles for Waterloo's ION. There was an option for an additional 16.
Likely, once Bombardier finishes off with this initial Freedom order, they'll go full throttle to build the outstanding Bombardier Outlooks for Toronto's legacy network. They maybe able to work on the Freedom order for Eglinton at the same time, but they would need to catch up on the Outlook order first.
Ah, interesting info. Though the Edmonton Journal reported that they'd started Edmonton roof assembly in Kingston last July. Hopefully they've advanced.I believe they already started the roof assembly (which is actually the first step) on the Edmonton order a month or so ago.
Different assembly lines. The TTC cars are coming out of Thunder Bay. The initial plan was to have one assembly line there that could churn out 39 cars a year (and I'd assume another churning out Freedoms). Now there are two assembly lines in Thunder Bay, that they hope to churn out 76 a year. Though they are making progress given they shipped 16 last quarter (and would have been 18 if not for their parts problem). That can do 64 a year now, and should be able to finish the TTC deliveries by November 2019 if they can ramp up a bit more.Likely, once Bombardier finishes off with this initial Freedom order, they'll go full throttle to build the outstanding Bombardier Outlooks for Toronto's legacy network. They maybe able to work on the Freedom order for Eglinton at the same time, but they would need to catch up on the Outlook order first.
Oh, Eglinton is single cab. I can't keep track. So what is to come of these 5-car double-cab ones for Metrolinx?There is absolutely no room in Kingston's production schedule for 2 re-tooling shutdowns (1 to produce Outlooks, the other to return to Freedoms) when 10 7-module Freedoms need to be in Edmonton by July and the first 5-module single cab Crosstown vehicles need to be shipped by the end of December.
Likely cancelled. Likely to refit and sell the dual-cab pilot to Waterloo for cheap. Especially since Metrolinx basically did nothing with it, including acknowledging its existence.Oh, Eglinton is single cab. I can't keep track. So what is to come of these 5-car double-cab ones for Metrolinx?