Toronto One Crosstown Towers I, II, III, and The Crest | 129.86m | 39s | Aspen Ridge | Core Architects

Progress Update:

The Crest: 7th floor forms visible in the Eastern part
Westernmost tower: 4th floor forms being put in place
Middle tower: 1st floor wall forms being put in place
Easternmost tower: Still pouring P1 wall forms

IMG_8177.jpg
IMG_8179.jpg
IMG_8180.jpg
 
Progress Update:

The Crest: Work ongoing on the mechanical penthouse floor
Westernmost tower: 6th floor forms being put in place
Middle tower: Hard to see, but still looks to be on the 1st floor wall forms
Easternmost tower: 1st floor wall forms being poured

img_8504-jpg.499299

IMG_8505.jpg
IMG_8506.jpg
 

Attachments

  • IMG_8504.jpg
    IMG_8504.jpg
    317.3 KB · Views: 892
Progress Update:

The Crest: Still working on mechanical penthouse, progress from here will be harder to see (E.g. interior, wiring, plumbing, etc.) until cladding starts installation
Westernmost tower: 8th floor wall forms in place
Middle tower: Hard to see, probably on 2nd floor
Easternmost tower: 2nd floor poured in some places

IMG_8597.jpg
IMG_8596.jpg
 

Back
Top