The floorplate is getting larger with every floor as the north façade is canting outwards. It won't cant inwards until the top dozen or so floors.
Didn't UT run an article a few months back where a Cityzen representative said it will be 4 days per floor now?
Is it possible the weather wall is moving up every 2 floors vs. 1? It seems pretty tall.
Unlikely and no.
I found the article: http://urbantoronto.ca/news/2011/10/interview-sam-crignano-cityzen-part-1
The very bottom says 4 days. Or did they mean something else?
So between March 26 and September 3 they built 7 floors in 161 days (= 3 weeks per floor). In comparison, 10-11 days per floor isn't so bad.