drum118
Superstar
From Topflight south of 407 to Matheson, all traffic light intersections have temporary construction lights installed, but not working. Derry Rd, 401 and Britannia are still waiting for poles to be install that are laying on the ground.
The new MSF is almost centre between Kennedy and Hurontario that is fully graded and waiting foundation for the steel structure.
The median has been removed from the 401 bridge and up to Britannia intersection. Some median remains at the traffic lights for the 401 westbound off ramp.
All the median from 407 bridge including the trees to Ray Lawson is gone and pave over. The median from the 407 to Topflight still exist for some odd reason.
The centre piers in the centre of the 407 fully built with a missing section with rebar between then and the Hurontario overpass. The rebar will be form when bridge work take place.
Photos to follow once I get the back log in front of them done.
The new MSF is almost centre between Kennedy and Hurontario that is fully graded and waiting foundation for the steel structure.
The median has been removed from the 401 bridge and up to Britannia intersection. Some median remains at the traffic lights for the 401 westbound off ramp.
All the median from 407 bridge including the trees to Ray Lawson is gone and pave over. The median from the 407 to Topflight still exist for some odd reason.
The centre piers in the centre of the 407 fully built with a missing section with rebar between then and the Hurontario overpass. The rebar will be form when bridge work take place.
Photos to follow once I get the back log in front of them done.