Toronto Bayview Village Redevelopment | 113.99m | 30s | bcIMC | DIALOG

I see an elevated walkway from towers to the mall in the render, but not in the overhead plans. Assume they will have that?
 
20200429_212050.jpg

From the link above.
 
We'll only get beautiful buildings if consumers demand it. We don't so they keep doing what they've been doing. Agree that it's depressing but things are better than they were 10 years ago. I try to focus on that.
 
A Site Plan Approval application was submitted on October 23, 2020:

2901 BAYVIEW AVE
Ward 17: Don Valley North


Site Plan application to permit the proposal for the South development consisting of two towers with proposed heights of 29 and 30 storeys connected by a single podiumn building for a total gross floor area of 65,670 square metres, 50,350 residential gross floor area and 15,320 non-residential gross floor area; 682 residential units, of which 26 units would be affordable rental units (OPA AND ZBA Application: 17 208789 NNY 24 OZ).

1617235611599.png


1617235695979.png


1617235718232.png


1617235738060.png


1617235757670.png
 
Last edited:
So one reason for a hold-up here, and it's a good one, is that approval here came with the dreaded 'H'.

The holding by-law that makes approval conditional on certain infrastructure improvements being completed first.

In this case, upgrades to the sanitary sewer. Those upgrades are now complete; and a report to the next meeting of NYCC recommends lifting the H.

 