I just checked. The ROW at Mill St is 22 meters wide(72 feet), but further west it looks to be 30 meters (100 feet). The south track looks 100% possible but a north track would require the heritage building to be moved a couple of meters north. As well the reconstruction of a few bridges at Main Street, Queen Street, Etobicoke Creek, Center Street,We are talking about RER service on the Milton line. How would there be ANY cost from CN? I'm really baffled here.
Obviously there's be significant money going to CP.
I'd think there'd be space - the ROW looks to be over 120 feet wide - is that enough for 6 tracks? 5 for sure.
Can they do 2-way all-day with just one new track and a grade separation? There's already 3 (and in some places 4 tracks) almost all the way west to Brampton, and then from just west of Brampton to past Mount Pleasant.