Overnight work slated for this weekend (Jan 25-27) at Marilyn to Havendale
Important track diversion work takes place this weekend, as contractors shift the old existing track next to the newly laid second track. Due to the safety of everyone involved, this will require 24-hour a day work beginning tonight, and ending Sunday morning. On Sunday evening, beginning at around 6pm, test trains will be running. This track diversion will take place from Marilyn to Havendale, as well as from McNicoll north. Residents will hear some moderate machine work during this time. We apologize for any inconvenience.
Overnight Tunnel Work at Agincourt GO weekend of Feb 8-11
EllisDon Transit Infrastructure (EDTI) is undertaking the construction of the Stouffville Stations Regional Express Rail Project on behalf of Infrastructure Ontario and Metrolinx. This project includes infrastructure improvements to the Agincourt GO, Milliken GO, and Unionville GO stations, and the construction of a grade-separated pedestrian bridge at the railway crossing Steeles Avenue East, between Redlea Avenue and Old Kennedy Road.
As part of the project, EDTI will be working within the Agincourt GO rail corridor starting Friday, February 8th, at 9 p.m. until Monday, February 11th, at 4 a.m. This work involves installation of the south pedestrian crossing tunnel at Agincourt. To ensure worker and public safety, nighttime work will be required over the weekend.
WHAT TO EXPECT
Daytime construction and up to three consecutive nights of work starting Friday, February 8th, 2019. Residents will hear construction-related noise during this time. Additional lighting will be used for safety during construction. As work will be restricted to off-peak hours, there will be no impacts to GO customers or train service. Work may be rescheduled due to weather or unforeseen circumstances.
Part I (Marilyn to Finch)Construction Update
Work Performed/Construction Activities:
- Collected ballast samples from existing north track for laboratory analysis
- Helped to collect ballast samples from existing north track from Marilyn to McNicoll Avenue crossing.
- Total 10 set of samples from 10 different locations were collected for laboratory analysis.
- Installed wires with south track leads at Finch and Havendale road crossing as part of south track activation
- Installing stakes for diversion of south track at north of Marilyn and South of McNicoll Avenue crossing.
Work Scheduled for This Week:
- Dewatering (When required)
- Preparing cabling for track diversion and installing shunt
- Track diversion preparation