SaugeenJunction
Senior Member
They need the extra platform once the new track 1 is installed. This will allow northbound trains to use track 1 and southbound track 2. UPX would continue to use track 3 & 4.
Based on all meetings for the station and the corridors over the last decade, the platform is to be a centre one to allow an 1A on the east side that would connect to CP track for the line to Bolton. Don't know if that still the case or not. If not, it would be a side one.
Track 1 is installed north/west of the station to south/east of hwy 401.
It would allow VIA to stop there if they want to.
So it would roughly go where I've drawn the measurement line I guess. I'd assume that another platform at Bloor GO is also in the works?