Here is some commentary that came my way as a year-end look at things related to GO Expansion, er, RER. I presume the "we/our" in the text is Metrolinx talking.
I posted other bits of the commentary in the threads dealing with USRC and Union Station.
- Paul
On the Horizon – OnCorr early works
Metrolinx continues on-track to bringing its core communities across the region 15-minute two-way all-
day service to get you where you need to go – better, faster and easier. To deliver this service, Metrolinx
will soon be beginning early works to build new track and signals, construct new rail facilities, modify and
build bridges, improve crossings and build electrification infrastructure across the GO network. Our first
priority is to orchestrate the relocation of utility works that are positioned throughout the corridor. As
work schedules are determined communications will be shared with neighbouring communities.
Ontario Line Early Works in USRCE
Work associated with the Ontario Line, overlapping the USRCE, will continue with geotechnical drilling
and surveying into 2021. Early works construction will also begin in 2021, when teams begin work on the
Lower Don Bridge modifications, station work, utility relocations and rail corridor expansion from Eastern
to Logan Avenue. Major construction for the rest of the project (including the Corktown Station and the
Don Yard portals) will begin in 2023. Additional reports will also be released next year, including the
Environmental Impact Assessment and Early Works Reports, which will detail potential impacts of the
project and mitigation measures Metrolinx will deploy. For more information, feel free to reach out via
email (
OntarioLine@Metrolinx.com) or consider signing up for the Ontario Line e-newsletter to receive
project updates.