Road paving has no bearing on testing the line and don't expect real testing will get underway this year. If real testing starts in January or February, the line could be in service by June or sooner. It could be later depending when testing starts.Isn't it minimum 3 months of testing for the TTC? Feel like even the road paving won't be done for january 1st
There maybe some testing this year to do the burn in requirements as well training and need to have a look which will not happen until late Oct at this time for me.