I wonder what the reference for that is.
The
$3.2 billion was from the city's October 2016 one station cost, using escalated (year of spending) dollars. Earlier there was a $3.56 billion estimate in 2015 (2014?) - but wasn't that for the 3-station version, using 2014 dollars?
So what's this $3.35 billion? Is that for the city's one-station plan (which is still proceeding)
or the province's thee-station promise (of which there's been no action)? Is that in escalated dollars
or a given year?
edit - to answer my own question.
The subway estimate of $3.2 billion is unchanged from ...actually
June 2016 ... to be more precise it's $3.159 million. In
February 2017 they added $0.187 for the "Triton Bus Terminal", to come to a total of $3.346 ... aka $3.35 billion.
All escalated costs.