Toronto Valhalla Village | 123m | 38s | KingSett Capital | Zeidler

Bringing down the last building core.
DSC_5841.jpg



Elevator rails

DSC_5818.jpg
 
December 4th update:
Not long to go to complete the demo. Centre core of 304 building coming down fast which just leaves the west side of the underground parking.
Water cannon was utterly useless today. All it did was serve to soak the road, passing cars and pedestrians. Dust from the demo was carried by the winds above and over the water spray.
No video due to high wind.

Obligatory weekly comparison shot:
DJI_0667.JPG

DJI_0672.JPG

DJI_0676.JPG
DJI_0685.JPG
DJI_0682.JPG
 
Dec 19th - And not much left. Some of these need some colour correction but no time for that today. These are all straight from the camera as shot.

DJI_0741.JPG
DJI_0742.JPG
DJI_0743.JPG
DJI_0744.JPG
DJI_0739.JPG
DJI_0745.JPG
DJI_0750.JPG
DJI_0751.JPG
 
Dec 28th
Very little change evident compared to Dec 19th.
DJI_0979.JPG
DJI_0982.JPG

DJI_0985.JPG
 
Welp...the painful part of this has finished. Now I am free to watch further progression of this project without my guts emotionally wrenching...

...it's wierd the things I've always liked sometimes.
 