TTC doesn't take deliveries on the weekend, with June 29 being the last day to receive a car.
Regardless if its 45 days or 52, cutting delivery close. Its still about a car arriving every 4 days at Hillcrest.
The last car has to be ship from TB by June 22 to allow CP time to delivery it by June 29. Thats makes it 45 days.
I would agree that they would have 45ish days to build cars. But I was replying to your previous post which I believe indicated that they had 45 days to have them here, which implies included transit time.