I was using the 43 that TTC reported in the last monthly CEO report.
If that site says 4466 was in service in Q1, it is not correct - it entered service the early hours of July 1, and it appears that TTC counted it as a Q2 car. Not sure quite how they got that 18th Q3 car. The day it entered service, is not necessarily the day TTC accepts the car. edit ... looks like TTC accepted 4500 on October 1, with it entering service on 5 AMish on October 2 ... I'd have counted that as Q4 not Q3 - but hard to quibble about 29 hours ...
View attachment 165189
4466 arrived Q1 and Q2 and enter service July 1, Q3, but what is day going to do being late, when it was already late.
4485 was the last car to enter service for Q2 on June 27, giving TTC 26 cars for Q2 including 4466. 4487 was the last car delivery for Q2 on June 28, giving TTC 28 cars on property.
4494 was the last car to enter service on Aug 31, giving TTC 35 cars in service for Q3. 4496 was the last car for Q3, giving TTC 37 cars on property for Q3
4502 was the last car for Oct 19 date to be in service for a total of 43 cars and 45 on property. This leaves 19 more cars due Q4 to be delivery or in service how you want to call it.
Today, TTC has 4511 on property for 52 car, still 12 cars short of year end schedule. TTC has 49 car in service today.
2 more cars could be on TTC property by the end of the week, depending on CP. TTC will have one more car in service this week and another next week. No clue as to when 4408 will see testing or have it GPS turn on and only been on TTC property 22 days so far. Wouldn't be the first car to enter service over 30 days after arrival, other than 4466.
With 5 work week left in the year, BBD is going to be hard press to have all the cars on TTC property per schedule, with the last off loading day being Dec 21. It could be the 27, 28 or 31, depending on CP. 2 are supposed to be coming from Kingston that is already a month late and the other 8 from Thunder Bay. Thats 2 cars a week now for Thunder Bay. The last of the 8 cars has to be ship Dec 14 and hope CP can get it to TTC by the 31.
Math says, TTC may have 64 cars on Property for this year schedule, but will be well short of those numbers to be in service.
If car 4523 shows up by year end, Thunder Bay only has to produce 4424-4469 in 2019 for a total of 43 cars.
If Thunder Bay produce the remaining cars like this year, the last one will be ship early Oct, ahead of schedule or Nov time frame. At this time, we have no idea how Kingston is going to preform and they only have 34 to do, including the 2 that are due this year.