idc24
Active Member
Any word on potential major retail tenants for the retail centre?
Ugh this is 5-7 years from completion?Any word on potential major retail tenants for the retail centre?
Allied, Enwave and Riocan to accelerate expansion of thermal energy system in Toronto
New thermal energy storage tanks at 'The Well' development will provide year-round, low-carbon cooling and heating services to Toronto's downtown west.
TORONTO, Feb. 8, 2018 /CNW/ - Allied Properties REIT ("Allied") (TSX: AP.UN), Enwave Energy Corporation ("Enwave") and RioCan REIT ("RioCan") (TSX: REI.UN) are joining forces to extend Enwave's existing Deep Lake Water Cooling and hot water distribution networks by building a new energy storage facility housed at The Well. The Well is a mixed-use residential, commercial and retail development by RioCan and Allied located in Toronto's downtown west. This joint undertaking will enable westward expansion of Enwave's system, providing both The Well and surrounding communities with access to sustainable cooling and heating solutions. This collaboration is the first one of its kind in Canada and the long-term business agreement will deliver value far into the future.
"This initiative is special in that three, forward-looking companies are collaborating and enabling pioneering ideas to be implemented at a scale greater than each company could achieve alone," said Carlyle Coutinho, President & COO, Enwave Canada. "The development is a reflection of our joint commitment to build resilient, urban communities incorporating intelligent energy solutions and utilizing future-focused technologies."
The thermal energy storage facility consists of two 6-million-litre tanks underneath The Well. The tanks will store temperature-controlled water fed by Enwave's existing Deep Lake Water Cooling system and a newly developed high-efficiency hot water network. It will expand the existing system's capacity with the ability to serve over 20 million square feet of commercial, retail and residential space. As an anchor site, the installation will serve The Well community, and buildings in neighbouring areas, providing the first low-carbon, resilient cooling and heating option for the downtown west community.
"This agreement enables the extension of Enwave's system to The Well and allows our tenants as well as commercial, retail and residential sites in the downtown west and surrounding areas to conserve energy and reduce Toronto's carbon emissions," said Ed Sonshine, Chief Executive Officer of RioCan. "This is a growing focus for many Canadians and we are excited that The Well will support these objectives."
This project will provide long-term benefits for the City of Toronto and support its focus on resiliency and carbon emission reduction. By decentralizing energy supply and reducing the load on the electricity grid, particularly during periods of peak demand, it enables a more reliable and flexible source of energy.
"This is a continuation of our ongoing community-building in King West," said Michael Emory, Allied's President & CEO. "The Well will now actively support two elements of a modern and progressive city: resilience and the need to decarbonize municipal energy supplies. As a mix of different occupancy types exerting their energy demands at different times of day, The Well is ideally suited to a system like Enwave. Also, in facilitating Enwave's expansion, The Well will enable the greater King West community to tap into a low-carbon cooling and heating source."
The Well features 1.1 million square feet of office space, 500,000 square feet of retail and food service space, and 1,800 residential units. Construction on The Well commenced in 2017.
February 8th update with photos.
Midday today, the following activities were ongoing:
Photos, starting with the North-East corner, working south towards the Front and Spadina intersection, and then west along Front Street. (Have to do this after having been piped at the post by someMidTowner - his post on the collaboration with Enwave was seconds before I could hit enter with mine.)
- On the north side, Wellington Street frontage, excavation was underway in preparation for installation of the retaining wall components, and towards the north-east corner, a crew was installing the lagging;
- Along the west side of the 401 Wellington Building (east side of the lot, south of Wellington) a shoring machine and crew were working away
- In the south east segment, four excavators, a welding crew, and a shoring machine were all working
- The shoring machine was working along the west perimeter of the site.
- My rough count (a challenge with so many pieces of equipment moving around) now eight excavators of various sizes now on the site, six of which were working concurrently earlier today.
View attachment 134403
Tieback activities beside the 401 Wellington West Building
View attachment 134404
View attachment 134405
View attachment 134406
View attachment 134407
View attachment 134408
View attachment 134409
A 'Sign' of things to come - by the gate on Front Street - 'Gate 8'
View attachment 134410
View attachment 134412
View attachment 134413
And finally, an overview image of The Well site (from our living room window):
View attachment 134414