Toronto The One | 308.6m | 85s | Tridel | Foster + Partners

Part 1 of 3 taken on August 20, 2023:

Bay and Cumberland:

IMG_9661.jpeg
IMG_9662.jpeg
IMG_9663.jpeg


Balmuto side:

IMG_9664.jpeg
IMG_9665.jpeg
IMG_9666.jpeg


Bloor side:

IMG_9667.jpeg
IMG_9668.jpeg
IMG_9669.jpeg
IMG_9670.jpeg
IMG_9671.jpeg
IMG_9672.jpeg
IMG_9673.jpeg
IMG_9674.jpeg
IMG_9675.jpeg
 
Part 2 of 3 taken on August 20, 2023:

Yonge and Bloor (aka the Golden Corner or the Champagne Corner):

View attachment 501600View attachment 501601View attachment 501602View attachment 501603View attachment 501604View attachment 501605View attachment 501606View attachment 501607View attachment 501608View attachment 501609View attachment 501610View attachment 501611

Bloor Street between Bay and Yonge is blocked off, though local traffic can use Balmuto
Any news on if Apple is still going to be the anchor?
 
I believe there's 54 floors to go still. If they average a floor every 8 days that would be 432 days from now. But I think the average floor is taking longer than 8 days. I think it's 9-10?

So about 500 days or so. Or December 2024, or 1 year and 4 months to go.
 
Not to put too fine a point on it, but 594 days (54 floors x 11 day average). Add two weeks for each mechanical section (optimistic) makes it the summer of 2025. Just one person's opinion...
I think there are only 49 res floors to go (mechanical sections are included in the floor count) but regardless I don’t see it topping out before late spring or summer 2025.
 
I expect they will complete many coming floors within 7 days (per). IIRC, they've already completed some floors in 7-8 days.
They have completed some floors in eight, I'm not aware of any in seven. The average slab for levels 19-36 was 7 days, and walls 4 days, thus my 11 days. Regardless, we have a lot more time to enjoy this project.
 

Back
Top