They are finishing third floor at the moment. From the 4th floor and up they make one floor a week. It should be on time. We are setting up decor centre with finishes for 500 St. Clair. You'll receive a letter soon. It will start from lower floors up, so your appointment could be a few months from now.
April 5 - working on the 5th floor now. Tentative occupancy date is early 2010 according to sales office
Oops sorry I moved the images to a different image site so they should work now.welcome to UT wongnog ... for some reason your images are not showing ~
seeing that they are on the 5th floor now out of 22 floors, estimated occupancy of early 2010 will be just that, an 'estimate' ... I suspect the realistic occupancy would be July-August 2010 at best?