Tracks are been upgraded as well switches.
In the coming weeks, the current 3 tracks on the south side will have to be shift or 3 new tracks built so the lines can be place over the green bridges at Queen St as well over the new Dufferin St underpass so rest of the underpass can be built to connect with Queen St.
At the same time, tracks at Bathurst St yard have to be extended to the west for the 12 car trains that will be store there during the day.
Then there is the building of the new 3rd track for the fly under.
CN in the last few weeks have been doing a lot of work for Bathurst Yard that they now have 5 tracks fully connected to Union Station with 2 more to be install. Up to then, there were next to no tracks or switches.
Expect to see another open house for this project before construction starts with time line how it will be built.
In the coming weeks, the current 3 tracks on the south side will have to be shift or 3 new tracks built so the lines can be place over the green bridges at Queen St as well over the new Dufferin St underpass so rest of the underpass can be built to connect with Queen St.
At the same time, tracks at Bathurst St yard have to be extended to the west for the 12 car trains that will be store there during the day.
Then there is the building of the new 3rd track for the fly under.
CN in the last few weeks have been doing a lot of work for Bathurst Yard that they now have 5 tracks fully connected to Union Station with 2 more to be install. Up to then, there were next to no tracks or switches.
Expect to see another open house for this project before construction starts with time line how it will be built.