There are a number of locations that need to be reglazed, but they aren't a priority at the moment. Primarily because, logistically, it's not feasible to re-rig swingstages that are currently in use for installation to go down and change mismatched glass or replace broken glass. This would unacceptably hamper forward progress on the tower. Swingstages crossing the install floor would also interfere with panel installation. It's also a safety concern to have a second set of stages working below stages operating on the upper tower, or while curtain wall is being installed.