Also up for consideration at the same meeting is the 2025-2034 capital budget plan.
From the above:
View attachment 606201
Of note here are the delays to the Dawes Road project pushed to late '25, for a start...........
Parkdale pushed out several years........... the importance of this is that it means the entire Parkdale Hub timeline is likely in jeopardy.....
@HousingNowTO
St.Lawrence appears to have some design money in '25...but construction is pushed to late '26 / early '27
@DSC
****
Then there's the projects that have fallen off the funded list entirely, for now:
City Hall is no surprise..........
But long contemplated Llllian H. Smith is on hold..........
The forever delayed project at Danforth/Coxwell has no beginning in sight, never mind an end.........
Meanwhile the Deer Park relocation deferral suggests possible delays to the Wittington project to which they are supposed to be relocating.