Toronto Post Loft Condos | 25.16m | 6s | Condoman | Standard Practice

There was a machine of some sort here the other day?

IMG_5392.JPG


IMG_5398.JPG


My first two photos here. Merry Christmas!
 
Last edited by a moderator:
Pardon my ignorance . So does this mean it’s starting soon? I live nearby you see and have been wondering if this was dead because it’s been sitting inactive for a such long time.
 
Pardon my ignorance . So does this mean it’s starting soon? I live nearby you see and have been wondering if this was dead because it’s been sitting inactive for a such long time.

Yeah, this should be positive news. A shoring permit means that they should have a pile driver type machine on site sometime soon to start preparation for upcoming excavation.
 
Last edited:


Forecasted development timeline:

• Excavation and shoring: from November 2021 to February 2021;
• Below grade formwork: from February 2021 to May 2022;
• Above grade formwork: from May 2022 to December 2022;
• Building envelope phase: from April 2022 to November 2022; and
• Interior finishes stage: from June 2022 to May 2023.
 