Toronto Portland Commons | 71.7m | 15s | Carttera | Sweeny &Co

Oct 18, 2022


3693055E-4313-4E9C-A27D-0624CBEEBBF4_1_201_a.jpeg



CFA2FAF1-CF53-408B-B94D-7F8A0B759D52_1_201_a.jpeg



52FD6280-0671-45C7-83D9-DD4F19C8E59A_1_201_a.jpeg



5C2B5DF8-BB72-41BF-A83E-4E4B71ECD26E_1_201_a.jpeg



8F439C56-EC1D-419D-8D68-6C212D2927CB_1_201_a.jpeg



57F608BC-9B7F-431C-AB0C-04FC658CE9E0_1_201_a.jpeg
 
Friday, December 9, 2022:

Pouring and smoothing concrete for a portion of the seventh floor. Considering the size of the Portland Commons building floor plate, this one seems to have moved along quite smoothly and quickly. Construction crews are working regularly into the late evening hours, until after 10 or 11 PM after concrete pours. Saturday work is also quite common on this building.

20221209_111503.jpg
 