.... while a brand new 11km automated line with 6 new stations and bus bays, 1.5km of underground, total exclusive elevated rail for the non-underground part come in at $1.4 billion in Vancouver?
Because it didn't come in at $1.4bil, not even close. The total cost of the line was almost $2.1bil in 2009 dollars.
Hmm, all of a sudden those costs here don't seem so far out of line, do they?