great pics, everyone! Shangri-La sent out an email today with a construction update:
Construction Update
We are pouring concrete for Level 65
(out of a total of 66 residential floors)
Glass has been delivered for the last run of estates floors and glass is currently being installed on Level 58.
Topping off the building at the end of November and the crane is coming down in February.
We are framing demising walls on Level 42 while the interior walls have been framed up to Level 39.
Level 26 has been boarded and painted with kitchen cabinetry and bathroom stone and plumbing fixtures installed.
Also some sales info on the newly released penthouses:
"Westbank’s President Ian Gillespie recently announced details of the release of four ultra-luxurious, exclusive new penthouse suites on the 65th/66th floor, quickly pointing out that there are actually only three available, as one has already been sold to Gillespie, himself.
These newly released suites will range in size from 3300- 3500 sf., and will feature private internal elevator service, unsurpassed features and finishes, and a massive terrace of approximately 1,400 sf. Priced at over $9 million, these corner two storey penthouses will be the highest terraced residential suites in Toronto."