Active Member
Metrolinx BOD to approve it for the 2015 budget by year end
Tender is to be call in 2015/16 with construction starting in 2016
Completion around 2020 depending on the final approve plan.
Work is to start on the yard first and unknown where others will take place. Thinking is going both direction from the yard and opening in phases. Phase 1 between Sq One and Brampton Shoppers World or Downtown depending on what the out come of the downtown plan.
I'm sorry, drum, I know you're typically really well-informed, but how the heck can you claim to know approval dates and when and how tenders will go out when it is a matter of public record that there isn't any money put aside for this project and Metrolinx has said they need new taxes to make it happen?