Mississauga Hurontario-Main Line 10 LRT | ?m | ?s | Metrolinx

No chance it was ever going to be done this year - Eglinton and Finch have appeared ready to go for at least a year and still no opening date for either. Hurontario line is still really far from being complete

Is this project longer then the Eglinton crosstown?
 
Is this project longer then the Eglinton crosstown?
No - phase 1 is about 18 km (with a single enclosed station) and 18 stops. Phase 1 of the Crosstown is 21 km (with 14 enclosed (13 underground) stations) and Phase 2 (to Renforth) is about 10 km with 7 underground or elevated stations.

Hurontario is more comparable to the 10-km Finch West line with 17 stops and 2 stations.
 
No - phase 1 is about 18 km (with a single enclosed station) and 18 stops. Phase 1 of the Crosstown is 21 km (with 14 enclosed (13 underground) stations) and Phase 2 (to Renforth) is about 10 km with 7 underground or elevated stations.

Hurontario is more comparable to the 10-km Finch West line with 17 stops and 2 stations.


Thank you
 
No - phase 1 is about 18 km (with a single enclosed station) and 18 stops. Phase 1 of the Crosstown is 21 km (with 14 enclosed (13 underground) stations) and Phase 2 (to Renforth) is about 10 km with 7 underground or elevated stations.

Hurontario is more comparable to the 10-km Finch West line with 17 stops and 2 stations.
It has more or less the stops as finch but it’s almost as long as eglinton. It’s really a mix if you asked me.
 
I thought the extended loop was in discussion not an actual done deal.

There haven't been many specifics since the announcement around this time last year, but they did add and include it in the Building Transit Faster Act and the various powers it would give to speed up construction and expropriation.

ONTARIO REGULATION 682/21

I assume while federal-provincial funding discussions take place, design work is happening behind the scenes. They would be starting from scratch for the longer Confederation portion.
 