Staring Monday June 19 to Sunday June 25 at 10pm, Elm St W is close for utility relocation with route 3 on detour. Work was supposed to happen on Sunday with closure, but nothing was taking place. It supposed to be close next Sunday as well.
The car folks will enjoy the reopening of the full intersection on June 18, subject to weather. They have to pour the top coat for the track on the southside as well pave the gap between the guideway and the road.
no one working on the line other than a 5 man crew getting tracks ready on Top Flight for leveling and alignment so concrete can be pour to anchor them in place. Once done, the crew will move to the westside of the only entrance and exit for Comfort Inn.
No one working on the hwy 401 westbound off ramp that has the base poured and working on forming the road curb for the guideway. The same thing is suppose to happen for the eastbound off ramp.
The 401 overpass is ready for the guideway built on it.
Did a walking tour from Britannia to the 407 parking lot and wasn't sure how much I would see as I could see the rain coming as I left home. It started to spite as I near Top Flight that only las a few minute. Once home it poured.
Nothing much has happen for the Britannia platform nor the guideway going south that is missing. Tracks still not in its final place for Matheson. Form in Place for Bristol platform. Work underway for Courtneypark and Derry Platforms.
By the looks of things, switches will be place north of Traders as well north of Kingsway. Trader could be a double crossover while the area north of Kingsway will see 2 single switches.
Just south of Skway the first substation in place with grading taking place on both side of it. Never noticed it until taking the bus to Sq One, there is a substation at Top Flight on the west side and it partly shows up in one of the photo shots of the intersection.
The outbound track is being form just out of site along with poles foundations. May see that track in another month or so.
The bulk of the guideway built from Matheson to just north of the Kingsway have tracks in place with a few areas waiting for concrete pour as well having tracks install. There are 16 sections of rail on the 401 overpass waiting to be splice into 4 tracks for the close intersection for the 401 off ramp.
They have added more base to support the retaining wall for the ramp to Rathburn with the south side missing a lot of it.
One more intersection north of Courtneypark Dr to be close for the guideway along with the 401 eastbound off ramp, Britannia Intersection, Top Flight Intersection to complete the test area. Top Flight is setup to have the guideway cross the northbound lanes that is ready to shift the traffic to the new lanes once the guideway is in place. Once traffic is shifted, the centre guideway can be built to connect to the section north of Kingsway.
Since we are about 18 months way from the completion date, I am expecting it will be about Q2 2025 with service starting O3/Q4 of 2025 at this time Time will tell later on this year when we may see service.
At this time, there is no room north of Top Flight to add any more industrial unless Hydro One allows it under their system which I don't see happening.
Photos will start to be posted on Monday with over 200 of them.
The one thing I see that is odd is the centre pole foundation in the guideway.. Most are single ones with a number of locations having 2 side by side to 3 in the same location. Only a few so far that I have see, The other is the hydro running beside the tracks to/from the OMSF where the poles are next to the transmission lines and shorter than the ones being upgraded on Hurontario. Are they to be upgraded like the rest or left as is since the tracks will be used to move the LRV's in/out of the yard??
I see the guideway in place for the test area by late fall and maybe the OS will be in place by year end or Q1 2024. This also applies to the guideway to Eglinton