Nov 17
Time this line had a video
End up having a few spare hours and decided to take a video of the work to the north. Had to scrap the northbound video.
The curb is in place from Hillcrest to Eglinton on the east side now and expect to see traffic using the new lanes by Dec or when it is pave.
The centre section is fully dug up from Eglinton to south of Britannia Rd in various stages of construction for the guideway
Track in place for the southbound track for 2 blocks and hard to say if any concrete has been pour for them. Work taking place installing tracks for the northbound where the southbound one are.
The first haft of Matheson Intersection is ready for the first pour of concrete or will it be a one pour job this weekend.
Framing is taking place for Matheson platform on top of what has been pour up to date.
Earth being place over the guideway north of Ambassdor for a temporary sidewalk so the intersection can be close off to allow tracks to be place across it.
The centre section is mostly dug up to south of Top Flight
Traffic using the south side of Top Flight as it being dug up for the westbound road and the guideway.
The inbound track by the 407 Station is cover and no idea if concrete has been pour to anchor it down or protection to allow concrete to be pour in the next week or so. Concrete was being pour out of sight in the guideway area as there was no way of getting a shot from my location. Still no outbound track in place from where it ended around the bend to the 407 Station area