I have no idea at this time as to what is being built on the south side of Eglinton for the new GO/UPX station. It could be retaining walls to support the tracks that will be move to the west location or part of the station platform.

The main footing for the tunnel for the LRT trail tack and future extension was pour over a week ago that will connect ti the tunnel section west of the rail corridor. This will allow the tunnel to be built along with a tunnel from the Weston Rd entrance to the section already built under the RR tracks to the LRT/Bus stations.

Been told core drilling has been taking place on the west side of Weston Rd where the new extension is to go by someone who visit the site daily.
49476879973_8d00660019_b.jpg

49476880223_c8fe9ee691_b.jpg

49476880483_63a1bf8ce1_b.jpg

49476880768_2f42c6931c_b.jpg

49477586322_f2d47522ac_b.jpg

49477369301_6304076e28_b.jpg

49476884833_590d1eb762_b.jpg

49477590667_e5c361d56d_b.jpg

49477592097_5547e06a19_b.jpg

49477592342_6a5dbf9f27_b.jpg

49477592552_9f604d7279_b.jpg

49477374786_b60a6658bf_b.jpg

49477594202_1ba1798459_b.jpg

49477595017_c2d59e7507_b.jpg

49476890493_86beeea95f_b.jpg
 
March 12
It will be known by Mid to late April based on where construction is if there will be an Open Door Event for the area if the Open Door Event take place at the end of May.

From the outside you can see a lot of work is still required in the station, let alone building the trail track tunnel, the pedestrian tunnel and the new GO/UPX station. The overhead in the station is the same as Ottawa and TTC St Clair W Loop, with work still taking place on it. This work and work within the tunnel and station is stopping testing of trains on the mainline as well the lack of a signalling system.

Blue plastic is covering where glazing is to go near the top of the roof for the station.

More up on site for this thread as well Black Creek, Keelesdale and Caledonia.
49655546876_c4945ca8e5_b.jpg

49655546516_ab4e15aca5_b.jpg

49655825422_ff74a6a491_b.jpg

49655546081_71c6579aa4_b.jpg

49655006003_00a52741a9_b.jpg

49655823777_98838e2a68_b.jpg

49655544366_dc674f07ef_b.jpg

49655823372_9c1d822185_b.jpg

49655543461_af86ca8471_b.jpg

49655003333_d9dbbbf069_b.jpg

49655003138_5c391ae968_b.jpg

49655002293_8b11d159d7_b.jpg

49655002128_fabd946367_b.jpg

49655540746_bbbdcca44c_b.jpg

49655818292_dddaf0c7e5_b.jpg

49654998993_3190deaf9c_b.jpg
 
March 12
It will be known by Mid to late April based on where construction is if there will be an Open Door Event for the area if the Open Door Event take place at the end of May.

From the outside you can see a lot of work is still required in the station, let alone building the trail track tunnel, the pedestrian tunnel and the new GO/UPX station. The overhead in the station is the same as Ottawa and TTC St Clair W Loop, with work still taking place on it. This work and work within the tunnel and station is stopping testing of trains on the mainline as well the lack of a signalling system.

Blue plastic is covering where glazing is to go near the top of the roof for the station.

More up on site for this thread as well Black Creek, Keelesdale and Caledonia.
49655546876_c4945ca8e5_b.jpg

49655546516_ab4e15aca5_b.jpg

49655825422_ff74a6a491_b.jpg

49655546081_71c6579aa4_b.jpg

49655006003_00a52741a9_b.jpg

49655823777_98838e2a68_b.jpg

49655544366_dc674f07ef_b.jpg

49655823372_9c1d822185_b.jpg

49655543461_af86ca8471_b.jpg

49655003333_d9dbbbf069_b.jpg

49655003138_5c391ae968_b.jpg

49655002293_8b11d159d7_b.jpg

49655002128_fabd946367_b.jpg

49655540746_bbbdcca44c_b.jpg

49655818292_dddaf0c7e5_b.jpg

49654998993_3190deaf9c_b.jpg
Doubtful if Covid-19 isn't contained. And I don't think construction will finish by then.
 
Doubtful if Covid-19 isn't contained. And I don't think construction will finish by then.
Covid-19 is the big question mark today, but maybe a different story come May. Not been inside the station itself, hard to say what has to take place to finish it. The bus terminal and maintenance complex is complete and don't need Eglinton to gain access to the area. There are 2 major roads leading to the complex and are open. Fencing can be place around area where construction taken place inside the station, but don't expect the elevators will be working then.

The 2 tunnels will not be completed and will not be require for an Open Door Event. Wasn't in the country for the last Open Door event for the site.

The GO Station will not be complete until 2021.
 