My senses tell me, the UCW is scheduled to be installed in the coming week(s). Hopefully the concrete and fireproofing cycle takes advantage of this warmer weather!
I still can't believe where they're constructing this gem of a building. Before it was a GO Bus station, that was a little nothing parking lot where my parents used to pick me up when I got off the train as a kid. It's the ultimate in-fill project.
Doubling the diamond count in this view will be wonderful. At least for awhile….it’ll be impacted by 261 Queen East with crane visible in foreground of final pic (thankfully it’s a Pontarini, so hopefully decent). Then there’s 10 Front…I’d be happy with shaving about 50 stories off that banal box.
New crane support and section added on Sunday.
New yellow climbing wall being installed covering level 9&10. You can see the blue supports protruding on the north side of the 10th & 11th floor.
Looks like they will have a new hoist someday on the east side starting on top of the podium level 9.
Hoist is up to level 17 labeled on the blue gate. No level 13.
Concrete core up to level 36.
Core set back at level 23 and 33.
Nice sunny commute to work
Counter balance. Ignore the purple solar film
Red section fastened to the crane top. White section unbolted from the crane top. Abracadabra, halfway there after ~20 minutes of climbing.