A tender was passed through my office for 383 Sorauren and in the tender documents was the construction schedule.
According to the schedule:
-So far, the construction is on time: they're at the P2/P1 slab form/pour.
-They expect to be at ground level by end of August.
-They want from ground to the 6th floor finished by June of next year.
-They want to start occupying the building in June of 2016.
-Entire building finished and completely occupied by September 2016.
Did a little bit of an experiment on Saturday (June 6th). With Dundas West Fest going on and the launch of the UPX Train, I decided to wander over the 383 Sorauren job site and wait for two trains to pass in both directions. To my ears, you cannot hear the UPX trains pass at all; the 506/505 streetcar makes more noise going over the bridge than the UPX train does. Now, this was at 6:00pm and Sorauren was busy so when I returned at 10:30pm I decided to do the same experiment, this time by standing on the bridge on Dundas. Again, the UPX train made very little noise until it passed directly under the bridge. It has a certain hum to it that's very similar to the TR trains.
Anyway, that's my update.