Had to go out of town unexpectedly Tuesday and came home Thursday that allow me to see what taking place since my last trip.
Most of the light Mast are up starting just east of the James Snow Parkway to the west side of 25 with a few gaps.
The old bridges for the Credit River, Orangeville Line, CN Halton Sub are gone and will be replace by new ones. Sixteen Creek looks like the deck has been pour for it as well the center barrier wall..
Small crew on site working on new Light Mast piers as well a small section of the centre barrier median. Some other Infrastructure work was taking place in various location.
Main push should start in early April with the removal of the old broken up road and building the areas that still have to be done.
Traffic wasn't bad going west in the collectors, but backup in the express at Mavis where I got on. It was a bitch of slow driving of 40-70 from Cambridge west of 24 with stop and go to the point I got off at Winston Churchill and use the 403. Would had used 407 if it wasn't toll. This was off peak.
Glad I don't have to do this every day and those who do will be glad when it is done by the fall this year.
Most of the centre barrier median in place east of highway 24 with a few gaps and no light mast up yet.
Crews placing the form work on the new westbound bridge over the Grand River and could see a concrete deck by the end of March depending on the weather.
No photos for this trip.
There are a number of bridges still to be rebuilt for 5 lanes from 25 to 6, with the big work to be done for 6 which will be a mess when it happens.