In the coming months, the current center lanes will be move to the new collector lanes so the existing lanes can be rebuilt. The old existing bridge footing will be removed at that time.
Work has starting for building the tunnel for the eastbound cut off that will go under Hurontario St and connect to Britannia Rd.
The last section for the collector westbound lanes will be pour this week and this will allow the centre lanes to be move to these lanes. The eastbound collectors lanes will be finish this month.
3/4 of the rebar for the northbound bridge is in place with part of it ready for pouring.
Some landscaping is taking place.
The new north service road west of Hurontario St will run right beside the on ramp for the westbound lanes.
There is about 100 photos of the whole area up on the site.
In the coming months, the current center lanes will be move to the new collector lanes so the existing lanes can be rebuilt. The old existing bridge footing will be removed at that time.
Work has starting for building the tunnel for the eastbound cut off that will go under Hurontario St and connect to Britannia Rd.
The last section for the collector westbound lanes will be pour this week and this will allow the centre lanes to be move to these lanes. The eastbound collectors lanes will be finish this month.
3/4 of the rebar for the northbound bridge is in place with part of it ready for pouring.
Some landscaping is taking place.
The new north service road west of Hurontario St will run right beside the on ramp for the westbound lanes.
There is about 100 photos of the whole area up on the site.