i'm ok with the townhomes being there.... but they could have been done differently. kind of in a colonial style - with white stucco and black railings. not sure if i'm describing it correctly
 
yup....looks like all we have to look forward to is Chapelfor - which will be nice. It's supposed to have a farmer's market and cafe open during the morning/day and restaurant at night

To my knowledge, Chapelfor has gone bye bye. Signs are down, no permits issued and no buzz in the industry. Too bad.
 
I am wondering if they would do anything about that gigantic cell tower right next to the south side of the building... I think the owners of the lake facing units are in for a huge shock!
 
Tonight:

4522519006_e3c57a8993.jpg
 
wow - so they should be done by mid-may with the glass and they've already started the interiors for the lower floors from what I could tell (I saw floorplans taped to the windows... which would mean the interiors for those units commenced). I guess the only other major work that needs to be completed prior to people moving in at the end of July/beginning of August is the parking garage and lobby.
 
looks like there are only about 6 more floors to go. I heard that the plumbers might be going on strike starting May 1. Anyone else here that?
 
that's correct ... Plumbing trades worker strike is looming to begin May 1st
 
Small update from today:

Looks like they're on the 18th floor, 7 more to go! You can also see they're starting some work for KWL there in the front... Maybe 10 works on site and a few pieces of equipment.

23791_10150154278550037_535045036_12131249_3631629_n.jpg


and

23791_10150154278560037_535045036_12131250_2064254_n.jpg


and Bliss up to 13/14