Thanks Simuls,
If that's the case, would you think they're behind schedule? The way I see it, say the first move is on August 1st. Then to meet the 30-day inspection, the bottom units have to be ready by July 1st. At the rate of putting windows up at a rate of 1 floor per week and there are 10 floors left, that takes us into mid-June which gives them 2 weeks to finish the bottom floors which I don't think is enough time. Also, I think lately they're putting up windows slower than 1 floor per week. They didn't put up any windows last week even though the weather was gorgeous. They're progress is frustrating me a little.
Anyways, I'd still be interested to learn of some of the closing dates that were mailed in February if anyone is willing to share ... and any feedback from people who agree/disagree with me here. Cheers everyone.