I also just received my letter. I'm mid-building, and I've been bumped from Sept 2013 to January 2014. The delays on this building are unbelievable.
The first delay was two years and was because the city of Toronto took time to decide not to put up the $500 million for the arts lab
Then the city of Toronto allowed the builders time to find private investors for the arts lab.
When the money could not be raised for the arts lab they had to redesign the base of the building.
I do not mind the fact that the construction was not moving too fast during the main phase of construction. Too many condos go up way too quickly and end up with way too many deficiencies. This building is being built to last. There are a lot of big names behind this building and proud workers on the job in every aspect related to the construction of L-Tower.
I cannot wait for the grand opening when the building is registered. I hope there will be a light show and celebration on the street like they did last fall.
Upgrades:
The bathroom plumbing fixtures is a must do in my opinion.
The hardwood flooring in the kitchen is another highly recommended upgrade.
The rest is personal choice. The Kitchen faucet is simple to replace compared to the bathroom shower and tub fixtures.
Personally I like the full width and full height Bathroom mirror Upgrade for $200, worth it to me.