Hello! Tentative occupancy date (Sep 15) aside, does anyone have a guess to when the actual occupancy might be for a unit on the 15th floor? Trying to make some important decisions as I am relocating to T.O. in Sep. I am thinking there will be another delay… did anyone with a unit on the low floor get a new final tentative occupancy date recently? Thank you.
Major construction activities and associated timelines for the development are described below:
• Excavation and shoring: March 2021 to July 2021;
• Below grade formwork: July 2021 to December 2021;
• Above grade formwork: December 2021 to June 2023;
• Building envelope phase: August 2022 to August 2023; and
• Interior finishes stage: October 2022 to June 2024.