The Don River bridge near Langstaff Road is the southernmost bit of infrastructure that has a third track roughed in. From there north to Major Mac, a third track is possible, but from that point north, a third track would again require a lot of work.
Great to see the new construction roughing in the third track, but there are so many grade separations that would need to be altered to connect the roughed in bits that I don’t see this coming to fruition for decades.
I do wonder if we will see a tail track for turnbacks and layovers at Aurora or elsewhere. That would improve on the current need to deadhead south to Kirby when there are theough trains to Barrie in the mix.


- Paul

I think the bridge over Finch is large enough to support 3 tracks, is it not?

****

My overall read of the corridor is that 3 tracks look feasible (bridge replacement issues aside), south to Finch, after that the corridor tightens up a bit.
 
So we're talking about the possibility of express trains running to & from King City?

Is there space for a third, centre track through Downsview?
There is space for a third track, but as I mentioned before the possibility of it being used (anytime soon at least) is low
 
I wouldn’t put your money on Barrie Line express trains, but if they did happen then what you described is exactly what would end up happening
Barrie is 100 kilometres away. It would be absurd for the Barrie trains to make all stops en route given the stations planned at Spadina, Lansdowne (Bloor), Caledonia (Eglinton), Concord (Hwy 7), Mulock, and Innisfil in addition to all the existing stations, and given that there are going to be additional services running shorter segments such as to Aurora and Bradford. It would only make sense for those shorter services to serve all stops while the Barrie trains make limited stops south of Newmarket.

GO Expansion is supposed to deliver transformative travel time improvements, not merely local service that's slower than the lumbering diesel service we already have today.
So we're talking about the possibility of express trains running to & from King City?

Is there space for a third, centre track through Downsview?
Yes, Downsview Park station has space for a 3rd track and so do many of the bridges in North York. However the segment at and near the Snider grade separation (over the CN York sub) is not designed for 3 tracks so it's unlikely they'd build a continuous third track. A 3rd track from just north of Hwy 7 to just north of Maple would be long enough to allow an express train to overtake a local given that it contains two stations. Downsview Park station might get a bypass track but it would mostly just be useful to allow freight trains to pass through without being directly next to platforms raised for level boarding, and unscheduled overtakes in case of delays. With only a single station in the segment, local trains would need to have several minutes of delay added to the schedule waiting for the express train to overtake.
 
Last edited:
GO Expansion is supposed to deliver transformative travel time improvements, not merely local service that's slower than the lumbering diesel service we already have today.
GO Expansion definitely will do that, and travel times might just be good enough to not require express trains. Only time will tell though

(for the record I’m not disagreeing with you, I think Barrie express trains would be great)
 
Last edited:
Barrie is 100 kilometres away. It would be absurd for the Barrie trains to make all stops en route given the stations planned at Spadina, Lansdowne (Bloor), Caledonia (Eglinton), Concord (Hwy 7), Mulock, and Innisfil in addition to all the existing stations, and given that there are going to be additional services running shorter segments such as to Aurora and Bradford. It would only make sense for those shorter services to serve all stops while the Barrie trains make limited stops south of Newmarket.

GO Expansion is supposed to deliver transformative travel time improvements, not merely local service that's slower than the lumbering diesel service we already have today.

Aspirationally, I totally agree.... but I wonder whether the incremental tweaks to conflicting agendas ie frequency, and closer station spacing have muddled this.

It's a question of a) how far apart stopping trains on 15 minute headways can get before they are overtaken by a following express and b) how those third tracks are utilised to operate express trains in both directions at once. Otherwise the express will mostly happen at peak but the off peak trains will still be all-stops plodders.

Once one assumes 15 minute core 2way service, plus added stations at Caledonia, Bloor, and Liberty, a third track between Steeles and Lawrence is essential - running express all the way to Concord between stopping trains will be an exercise in catching up. The Lawrence-Steeles leg is buildable in the mid term, but interleaving two directional flow will be challenging. Very precise schedule adherence is demanded - lots of other operators achieve this, but it's a new ballgame for ML. .

There is also the question of cash flow.... I wonder what priority ML places on a third track and express format on this line as compared to other expansion needs eg Milton, Niagara, added stations. There is only so much money. I would guess that three tracks to Barrie is still a ways down the list.

Perhaps ML has this all modelled out and it looks fine on paper....I'm still a bit dubious from here in the bleachers.

- Paul
 
Metrolinx did build the Davenport Diamond as a 2-track structure after initially proposing it as a 3-track structure, from my understanding. So 3-tracks is limited by that.

The rest of the corridor can support it with the right infrastructure though, from my understanding.
 
Metrolinx did build the Davenport Diamond as a 2-track structure after initially proposing it as a 3-track structure, from my understanding. So 3-tracks is limited by that.

The rest of the corridor can support it with the right infrastructure though, from my understanding.
I brought this up earlier in the Davenport Diamond thread, and the prevailing response I got was three tracks wouldn't be necessary. Not sure I agree.
 
I brought this up earlier in the Davenport Diamond thread, and the prevailing response I got was three tracks wouldn't be necessary. Not sure I agree.

The issue with Davenport was more that the initial 3-track design left far less opportunity to create a useful public space down below. The two track design gives a lot more light and openness and enables an attractive linear park and pathway. Whereas with three tracks, one would be pretty much recreating the underside of the Gardiner. You can see why everyone "hoped" that wasn't necessary.

It may still be technically possible to add a third track, but the community reaction to that would be brutal.

And the issue is not just the guideway itself, there would have to be a lot of property acquired and civil works carried out to connect a third track from the north end of the guideway up to Eglintonish where the corridor widens. There has never been an intention to have more than two tracks between the south end of the guideway and Bathurst Street - again, adding a third dedicated to the Barrie line would be a huge expense in that stretch. Crossovers to the Kitchener line is all that would ever be needed.

I do think that two dedicated tracks for the initial section from Bathurst St to Eglinton is sufficient with appropriate signalling. Express trains would likely make some or all of the stops in that section anyways, so the only real need is installing signalling that can manage the added frequency.

- Paul
 
Barrie is 100 kilometres away. It would be absurd for the Barrie trains to make all stops en route given the stations planned at Spadina, Lansdowne (Bloor), Caledonia (Eglinton), Concord (Hwy 7), Mulock, and Innisfil in addition to all the existing stations, and given that there are going to be additional services running shorter segments such as to Aurora and Bradford. It would only make sense for those shorter services to serve all stops while the Barrie trains make limited stops south of Newmarket.

GO Expansion is supposed to deliver transformative travel time improvements, not merely local service that's slower than the lumbering diesel service we already have today.

Yes, Downsview Park station has space for a 3rd track and so do many of the bridges in North York. However the segment at and near the Snider grade separation (over the CN York sub) is not designed for 3 tracks so it's unlikely they'd build a continuous third track. A 3rd track from just north of Hwy 7 to just north of Maple would be long enough to allow an express train to overtake a local given that it contains two stations. Downsview Park station might get a bypass track but it would mostly just be useful to allow freight trains to pass through without being directly next to platforms raised for level boarding, and unscheduled overtakes in case of delays. With only a single station in the segment, local trains would need to have several minutes of delay added to the schedule waiting for the express train to overtake.
Freight trains don't really go south of Downsview Park anymore furthest south they hit usually between Finch or Sheppard
 
South of Sniderman to the Davenport Diamond will eventually have 2 stations once Caledonia GO is built. Not sure if that station is being designed for 3 tracks off hand though.

edit: yes, the TPAP for the station includes 3 tracks. So it would have a decent opportunity for express to overtake.

The TPAP interestingly includes a third platform for the express track as well though, so not sure on the thought behind that one.

Eventually the Highway 7 to Maple stretch will actually have 3 stations as well, which gives even more time for overtaking.
 
We got the Bradford Bypass when what we need* is the Aurora Bypass **

* okay nice to have
** yeah it looks crappy I did it on my phone
IMG_1162.jpeg
 
Bloomington station was partially built as a relief station for Aurora. The Richmond Hill line service however does not intice many from Aurora from using it.
 
Aspirationally, I totally agree.... but I wonder whether the incremental tweaks to conflicting agendas ie frequency, and closer station spacing have muddled this.

It's a question of a) how far apart stopping trains on 15 minute headways can get before they are overtaken by a following express and b) how those third tracks are utilised to operate express trains in both directions at once. Otherwise the express will mostly happen at peak but the off peak trains will still be all-stops plodders.

Once one assumes 15 minute core 2way service, plus added stations at Caledonia, Bloor, and Liberty, a third track between Steeles and Lawrence is essential - running express all the way to Concord between stopping trains will be an exercise in catching up. The Lawrence-Steeles leg is buildable in the mid term, but interleaving two directional flow will be challenging. Very precise schedule adherence is demanded - lots of other operators achieve this, but it's a new ballgame for ML. .
I've mocked up a timetable for the track configuration where there is double track to Barrie with one 3-track segment through Rutherford and Maple stations and it already accommodates half-hourly express trains from Barrie in both directions in addition to 4 local trains per hour. You only need a single overtaking location to accommodate the difference in speed, so there's no need for a 3-track segment at Lawrence.

In this scenario I assumed that the trains to Barrie are diesel and the local trains are electric. This would be the interim condition until electrification makes it all the way to Barrie. The stopping pattern I used for Barrie trains is all stops from Barrie to Newmarket, then limited stops to Union, stopping only at Aurora and stations with a direct subway interchange. There are so many new stations that even with this limited-stop pattern, express trains only stop at one fewer station than the current local trains.

I mocked up two options for the basic off-peak service, one using the passing track and one not. If Option 2 (no scheduled overtake) is chosen, the passing track would act as a plan B in case an express train gets stuck behind a local train due to delays. For example, if the 07:00 train from Barrie gets delayed and arrives at Aurora at 07:59, it can briefly run behind the 07:56 train until Maple where it overtakes it, arriving at Downsview Park at 08:22 with a clear shot to run fast to Union.

Passing track outlined in black. Times in blue are non-stop.
Screenshot 2024-05-30 at 15.33.03.png


Screenshot 2024-05-30 at 05.42.41.png



There is also the question of cash flow.... I wonder what priority ML places on a third track and express format on this line as compared to other expansion needs eg Milton, Niagara, added stations. There is only so much money. I would guess that three tracks to Barrie is still a ways down the list.

Perhaps ML has this all modelled out and it looks fine on paper....I'm still a bit dubious from here in the bleachers.
The cost of installing a third track through Rutherford and Maple is negligible given that the underlying structure is already in place - all that's missing is the track itself. There is no need to build three tracks all the way to Barrie.
 