drum118
Superstar
Tracks 2, 3 and 4 are in operation and have been since day one for Weston station. Track 1 is not completed and will not be completed until the new east platform is finish at Weston station.. Tracks at both ends in place other than the station.Union Pearson express uses the track between union and highway 427 and the north track might be closed off at Weston for construction
With the construction on going for the Mount Dennis Station, 2 tracks not in service for the new station, but a 3rd one as temporary one is in place.
Track 1 has yet to be built south of the Toronto West Diamond to Bathurst St or where it will become track 3 south of Dundas. Track 1 north/west of the Humber River is missing until the tacks are built in the tunnel under 401/409 as well building the new Woodbine Station. North/west of 427, all 4 tracks in place up to Bramalea.
Track 1 and 2 will be for the Barrie Line with 7 & 8 for the Milton Line south of Dundas