(as of July/08):
Finishes in the Building M suites are complete, with the exception of the hoist suites. PPDI inspections have been completed up to the 12th floor and suites have been certified up to the 9th floor. Corridor finishes are on-going.
At Tower L, concrete, structural steel and window wall activities are complete, while roofing and siding activities are on-going. On the interior, suite framing is complete and drywall boarding has reached the penthouse level. Kitchen installation is on the 39th floor with the countertops following on the 37th floor. Laminate flooring is being completed on the 35th floor, carpet on the 33rd floor and closet shelving and sliding doors are on the 30th floor. PPDI inspections began in late June.
Curtainwall and roofing at the Amenity Building are complete and interior finishes are on-going.