This is in no particular order as i just took it down in notes but ill try to be logical. I arrived after the main presentation but here is what i learned from the staff and Loblaw reps during questioning and such.
The main issue going forward with the project and one of the biggest issues with the repeat delays was simply the engineering contamination and heritage restoration costs for the site. Garrison creek runs only a few feet below the site which complicates things To address the financial viability of the retail/commercial project and the site conditions, the two condo towers were added to help out. The secondary plan for Fort York area contemplates the possibility of towers on this site however an OPA amendment will bee needed because they have to up the gross floor area of the site from the currently allowed 71,000 square meters to 76,000 square meters. The architects and loblaws arent happy with the design of the commercial box on top (someone called it an over sized air filter LOL) so its going to go back to a redesign. The whole project will eventually go through the Design Review Panel and refined.
The west tower is proposed at 37 stories and the eat tower at 31 storeys. Given shadowing issues on Fort York, the towers will likely be sculpted to reduce that or potential shortened by a floor or two. Loblaws is planning a partnership with a developer and builder to help with the development of the site. No word yet on who but my guess is PCL or Ellisdon. The retail and commercial part will come first. regardless whether the condos sell quick enough. If the market for condos can bare, then the whole project can be done in one shot or else there will be a phased implementation. parking will be both underground and at grade under the Gardiner.
After some confusion regarding the billboard heritage status and weather they will come back: they are not as of right allowed to come back since once they are dismantled for construction the builder must reapply to put them back up through the usual billboard application process. However loblaws does want to bring them back as part of keeping with their plans for the site.
While Loblaws was developing the site plan for the area they realized from their Queen&Portland location that they didnt need so much parking. The site was reconfigured to be less auto based with an increase in bike parking and pedestrian amenities. Parking in the condos west of Bathusrt has been less than expected and there will be likely approx 340 spaces for retail/commercial and about 600 for residential.
With regards to Traffic, the whole area is being studied as part of the billy bishop airport transport study. The affect of loblaws is being considered in this study. Lakeshore Bathurst intersection is currently a mind boggle for traffic engineers and they can possibly conceive why it is how it is and are having a difficult time figuring out how to improve it. The current hope is that the completion of Fort york boulevard, Housey Street and Dan Leckie Way will help to ease traffic congestion along lakeshore with alternate routes. Adam Vaughan said that hopefully the completion of the fort york connection will get under way "within a matter of months".
Loading docks will be located at an entrance off of Housey street and parking for the residences will come in off bathurst. The plan in a right in, right out on bathurst to ensure no left turns blocking traffic flow.
One of the most interesting discussions was about transit in the area. Some radical TTC streetcar ideas.
Given the Bremner/Fort York streetcar is likely never going to happen in our time due to funding outlays and other transit priority projects Adam Vaughan was talking about an idea which would see a free/TTC shuttle service operated in a loop From front/spadinat to Bremner across to Bathurst, back up to Front and back across to Front/spadina.
Addressing the east Bayfront transit needs Adam Vaughan was mentioning discussions with the TTC of running the bathurst car down to queens quay and to union station.Then TTC extending the spadina streetcar over to the east bay front with some sort of eastern extended surface track passed the Bay portal as a means of finding a lower cost solution to the east bay front tunnel which would be needed for a separate east bayfront line to enter union station. The result is frequent service provided to union station using streetcars for the folks in the condos south of the rail tracks and also to the people expected to be coming down to queens quay.
So thats a mouthful. Ask if you have any questions and ill try to clarify.