Ignore that. It was just hypothetical situation.Where did2028 come from….thats 5 more years
Ignore that. It was just hypothetical situation.Where did2028 come from….thats 5 more years
Can they change Outside occupancy date again? Can Tarion nothelpOutside occupancy is April 2025, it would probably take until then tbh
Can they change Outside occupancy date again? Can Tarion nothelp
No they can’t, unless there’s more unavoidable delaysThey would need another ‘unavoidable delay’ to change the outside occupancy date again, and for the record, Tarion is useless until we get our keys and close
Or make everyone signan amemdment?No they can’t, unless there’s more unavoidable delays
not sure about this.Or make everyone signan amemdment?
"Construction workers labour shortage"No they can’t, unless there’s more unavoidable delays
Has to be a critical Delay ack by the city o province i think..first need to see construction start then think about alternatives"Construction workers labour shortage"
Has to be a critical Delay ack by the city o province i think..first need to see construction start
The last 2 or more phases were sold as avg today prices but the first sales is where they may ask for price chgI think. They can’t make another unavoidable delay without any critical reasons. In case they ask amendments for dates, they would like to amend the price as well.
True.. Dont stress about it! When u see construction starts then u know! Which i think personally wont happen until after int rates start going .. So forget about what they say Oct they will startHmm. So many speculation. Let’s wait and see.
Had to delete my yesterday's post because I wanted to be sure of the facts...the new Heartlake collection project on 10194 hearlake road (current presentation office) has some legal issue. A CPL was issued in July 2023 and construction for that project will not start anytime soon until the case is resolved.
I believe the CPL is having some backslash on the Uptown project (our project) but I'm not 100% sure at this point. The is because a CPL on any of the builders project could be seen as a default event by lenders and a lender could withdraw all construction loan/ commitment letters. If this is the case, I don't see construction commencing on Uptown project. I hope I'm wrong.
For anyone calling Dominic, ask him how does the CPL impact the uptown project and if he's honest about construction commencing in October as he claimed.