Update on the project in report to Government and Lic. Committee meeting of May 21, 2019
From said Report:
Stage 2/3:
•Exterior restoration of the East Wing is 99% complete.
•Great Hall Restoration: East and West arches, including windows, north wall, south wall and ceiling cleaning complete.
The floor restoration remains outstanding.
•VIA Concourse restoration is 99% complete.
•Front Street West Moat: Moat cover installation is 100% complete.
•Front Street East Moat: Moat cover installation is 80% complete.
•East Wing ground floor is over 80% complete.
•Bay Concourse/Retail: Excavation, structural column replacements, and new Bay Concourse suspended slab and slab on grade completed.
•50% of the Commercial Retail Units in the Front Street Promenade have been completed and are currently operating.
•Interior finishing work is 65% complete.
Schedule Update and Future Milestone
The remaining work includes the completion of Stage 2/3, which includes the Bay Concourse, VIA Concourse, Great Hall, remaining retail areas, East Wing exterior façade, and the York and Bay Street moat covers. While significant progress is expected by the end of 2019, construction logistics require work on certain portions of the station to continue into 2020, including the Bay and Front Street moats. Total completion of the Stage 2/3 scope of work is anticipated by the end of the third quarter of 2020.
The USRP team has implemented a strategy to expedite ongoing construction and ensure that completed areas of the station open to the public as soon as possible. As sections of the Bay Concourse, Front Street Promenade, and remaining retail areas are Union Station Revitalization Project – Status Report & Contract Amendments Page 8 of 11completed in the second and third quarters of 2019, they will be turned over to Metrolinx and Osmington for interior fit-out prior to public opening. This staged turnover will lead to new areas of the station opening up as they are ready, which will contribute to improved pedestrian flow through the station and enjoyment of the commercial and retail amenities. Metrolinx and Osmington will ultimately determine exactly when these areas of the station open to the public. Based on typical construction schedules it is anticipated that remaining retail units will open on a rolling basis throughout 2020. The Bay Concourse is expected to be available for public usage in the first quarter of 2020.