October 23. First forms on the west side of the office tower have now moved up to start work on the 30th floor.
Cycle times per floor over the past months since early May have been:
Date..............Floor.........Days
May 1.............19................-
May 28..........20...............27
June 12.........21..............15
June 25.........22..............13
July 10..........23..............15
July 24..........24..............14
August 10....25..............18 (Includes the August long holiday weekend)
August 21....26..............11
Sept. 3..........27..............13
Sept. 21.......28..............18 (Includes the Labour Day holiday long weekend)
October 9....29..............18
October 23...30............14 (Includes the Thanksgiving Day holiday long weekend)