Toronto The Madison | 121m | 36s | Madison Group | Kirkor

Excavation continues unabated. Images taken this afternoon:

8235512857_bb5d4877a8_b.jpg


8236577906_8761ccc805_b.jpg


8236577772_107589a06a_b.jpg


8235512537_97109fafd8_b.jpg
 
..... and a east-west laneway on the southern limits of the site which provides residents dropoff areas and access to parking garage

great more people to drive the wrong way down Dunfield's oneway. LOL
 
Last edited by a moderator:
They seem to be taking their time with this one !
 
Seems pretty quick to me, they only started excavation a few months ago.

Really ! I thought it was longer, and I never see that much equipment on site ! Like the pic you took above ?
 
Really ! I thought it was longer, and I never see that much equipment on site ! Like the pic you took above ?

Excvation can only go as fast as the perimeter shoring...its a sequence...the perimeter shoring was installed in mid October so given that was only a couple months ago this one is moving along quite nicely..
 
Forgive the inexcusably crappy image quality (I didn't have my camera with me today so I took these with a PS Vita)
Today:

CxSf8wY.jpg


RGn8Sf8.jpg


Po9RBY9.jpg


GM8BwKS.jpg
 
Photos taken March 1.

SDC13040.jpg


SDC13041.jpg


SDC13043.jpg
 

Attachments

  • SDC13040.jpg
    SDC13040.jpg
    93 KB · Views: 823
  • SDC13041.jpg
    SDC13041.jpg
    97.9 KB · Views: 814
  • SDC13043.jpg
    SDC13043.jpg
    98.4 KB · Views: 820
They were putting in the dewater equipment by crane last week.

They still have to do a 5 meter cut once the dewater system is working.

The east tower crane is schedule to go up beginning of May.
 
The front page story we posted last month was incorrect (due to a misjudgment on my part) The excavation is in fact not complete.

More digging at the northeast corner of the site from today:

G7JfNBU.jpg


PGCVSnQ.jpg
 

Back
Top