Dec 26
Concrete work is completed with very little back filling to be done.
Steel on site to start the framing of the new south end entrance, as well for the rest of the expansion. They have added a new roof on top of the existing one on the north side of Hudson Bay. Looks like a 2nd level for the south side with a new connection the the Bay.
Not sure what up with the new truss framing on the slopping centre court roof and looks like a few more going to go up there as well.
Starting the wall framing on the west side.
Forever 21 miss all the various dates for completion as well missing the Christmas sale, but should open in Jan 2015, 4 months late.
The smoke place in the food court is gone with a new food place to open in it place. Taken a long time to moved that place out of there going back at least 15 years or more when other reno's took place in that area.
We may find out early 2015 what is plan for the next expansion. The next expansion should be the rebuilding of this mall into a smaller area along the Eaton Centre with 4 levels of stores as well increasing the number of them so the so call Downtown can be built on these lands. Its the white elephant in the city core.
Lot more up on site