Estimated construction timeline:
- Demolition: June 2021 to July 2021
- Excavation and shoring: from July 2021 to October 2021;
- Below grade formwork: from October 2021 to April 2022;
- Above grade formwork: from April 2022 to April 2023;
- Building envelope: from November 2022 to April 2024; and
- Interior finishes: from August 2023 to December 2024.
The lower units will start in Feb 2024.Is this occupancy?!